Loose Ends

As I returned to work, it was rather startling to see how much I hadn't finished since the last time the project came to a standstill. I created this checklist back in the fall of 2017 so I wouldn't forget anything. Items are listed in order of completion.

Task

Done

finish framing two of three windows in the office

08/11/18

install the HVAC compressor local disconnect box

08/11/18

install the septic pump control box

08/12/18

finish the blocking (ceiling edge supports) in the studio

08/12/18

finish the blocking in the bathroom

08/12/18

install the well hookup in the workshop

08/22/18

finish the plumbing for the utility sink in the studio

08/22/18

install the oven hookup electrical box

08/22/18

add the water line for the refrigerator icemaker

08/24/18

finish the blocking in the living room

08/25/18

install the main air return intake vent in the foyer

09/01/18

install the external vent for the bathroom fan

09/05/18

install the external vent for the dryer

09/05/18

finish installing hurricane ties in the garage

09/10/18

install the external vent for the exhaust fan in Kitty Central

09/29/18