Sidebar: Timeline

Some friends and visitors have asked about what took place when, so I decided to roll all of the milestones into a concise timeline.

  • 25 October 2013: Closed on the property.
  • 4 September 2014: Moved into camper.
  • 14 October 2014: Tree work completed.
  • 21 October 2014: Hired architect.
  • 21 January 2015: Property survey completed.
  • 14 February 2015: Wetland survey completed and approved.
  • 24 February 2015: Soil conservation application submitted.
  • 30 April 2015: Hired septic system engineer.
  • 18 June 2015: Obtained soil logs in advance of building septic system.
  • 27 July 2015: Applied for septic system permit.
  • 22 September 2015: Began building the guest house.
  • 11 October 2015: Began building treehouse.
  • 24 October 2015: Septic system construction began.
  • 26 October 2015: Moved into the guest house.
  • 5 November 2015: Septic system finished.
  • 3 December 2015: Zoning permit for construction obtained.
  • 11 December 2015: Blueprints finished and submitted to township.
  • 12 February 2016: Driveway graded.
  • 29 February 2016: Groundbreaking for foundation.
  • 2 April 2016: Foundation finished.
  • 7 April 2016: Framing began.
  • 26 April 2016: Well drilling began.
  • 11 May 2016: Well finished.
  • 1 August 2016: Principal framing completed.
  • 29 September 2016: Suspended all work on the house.
  • 6 July 2017: Temporary electric service panel installed.
  • 10 August 2017: Electric service connected.
  • 10 September 2017: Resumed work on the house.