Milestones

  • 25 October 2013. Closed on the property.
  • 4 September 2014. Moved into the camper.
  • 14 October 2014. Tree work completed.

  • 21 October 2014. Architect hired.
  • 21 January 2015. Property survey completed.
  • 14 February 2015. Wetland survey completed and submitted.

  • 22 April 2015. Wetland survey approved.
  • 30 April 2015. Septic system engineer hired.
  • 18 June 2015. Soil logs for septic system taken.

  • 27 July 2015. Applied for septic system permit.
  • 22 September 2015. Began building the guest house.
  • 24 October 2015. Septic system construction began.

  • 26 October 2015. Moved into the guest house.
  • 5 November 2015. Septic system finished.

  • 3 December 2015. Zoning permit for construction obtained.
  • 11 December 2015. Blueprints finished and submitted to township.
  • 12 February 2016. Driveway graded.

  • 29 February 2016. Groundbreaking for foundation.
  • 2 April 2016. Foundation finished.

  • 11 May 2016. Well finished.
  • 1 August 2016. Principal framing completed.

  • 30 October 2018. Permanent electric service connected.
  • 8 November 2018. First light.
  • 8 November 2018. Passed rough plumbing inspection.
  • 9 November 2018. Passed rough electrical inspection.

  • 13 November 2018. Passed framing/mechanical inspection.
  • 14 November 2018. Exterior doors installed.

  • 24 November 2018. Picture windows installed (center two were defective and replaced on 6 February 2019).
  • 29 November 2018. Roof finished and all small windows installed.

  • 17 January 2019. Insulation is finished.
  • 18 January 2019. Passed insulation inspection.

  • 4 May 2019. Toilet installed.
  • 8 May 2019. Porta-potty removed.
  • 9 May 2019. Moved into the house.

  • 1 October 2019. Shower is finished.

  • 9 June 2020. Removed the camper.