Milestones

  • 25 October 2013. Closed on the property.
  • 4 September 2014. Moved into the camper.
  • 14 October 2014. Tree work completed.

  • 21 October 2014. Architect hired.
  • 21 January 2015. Property survey completed.
  • 14 February 2015. Wetland survey completed and submitted.

  • 24 February 2015. Soil conservation application submitted.
  • 22 April 2015. Wetland survey approved.
  • 30 April 2015. Septic system engineer hired.
  • 18 June 2015. Soil logs for septic system taken.

  • 27 July 2015. Applied for septic system permit.
  • 22 September 2015. Began building the guest house.
  • 24 October 2015. Septic system construction began.

  • 26 October 2015. Moved into the guest house.
  • 5 November 2015. Septic system finished.

  • 3 December 2015. Zoning permit for construction obtained.
  • 11 December 2015. Blueprints finished and submitted to township.
  • 12 February 2016. Driveway graded.

  • 29 February 2016. Groundbreaking for foundation.
  • 2 April 2016. Foundation finished.

  • 11 May 2016. Well finished.
  • 1 August 2016. Principal framing completed.

  • 14 November 2018. Exterior doors installed.
  • 24 November 2018. Picture windows installed (center two were defective and replaced on 6 February 2019).