Milestones
- 25 October 2013. Closed on the property.
- 4 September 2014. Moved into the camper.
- 14 October 2014. Tree work completed.
- 21 October 2014. Architect hired.
- 21 January 2015. Property survey completed.
- 14 February 2015. Wetland survey completed and submitted.
- 22 April 2015. Wetland survey approved.
- 30 April 2015. Septic system engineer hired.
- 18 June 2015. Soil logs for septic system taken.
- 27 July 2015. Applied for septic system permit.
- 22 September 2015. Began building the guest house.
- 24 October 2015. Septic system construction began.
- 26 October 2015. Moved into the guest house.
- 5 November 2015. Septic system finished.
- 3 December 2015. Zoning permit for construction obtained.
- 11 December 2015. Blueprints finished and submitted to township.
- 12 February 2016. Driveway graded.
- 29 February 2016. Groundbreaking
for foundation.
- 2 April 2016. Foundation finished.
- 11 May 2016. Well finished.
- 1 August 2016. Principal framing completed.
- 30 October 2018. Permanent electric service connected.
- 8 November 2018. First light.
- 8 November 2018. Passed rough plumbing inspection.
- 9 November 2018. Passed rough electrical inspection.
- 13 November 2018. Passed framing/mechanical inspection.
- 14 November 2018. Exterior doors installed.
- 24 November 2018. Picture windows installed (center two were defective and replaced
on 6 February 2019).
- 29 November 2018. Roof finished and all small windows
installed.
- 17 January 2019. Insulation is finished.
- 18 January 2019. Passed insulation inspection.
- 4 May 2019. Toilet installed.
- 8 May 2019. Porta-potty removed.
- 9 May 2019. Moved into the house.
- 1 October 2019. Shower is finished.
- 9 June 2020. Removed the camper.